|
Seamless
Floors has recently designed and constructed a concrete floor slab for
Bluestone at Poole. The floor was suspended on piles and incorporated
steel fibres as the primary method of reinforcement. A gas venting system
was installed in conjunction with the slab construction therefore permitting
the use of laser screed machine and concrete placement by direct discharge.
The project highlighted the important role that flooring subcontractors
can now play in the design process.
Integrated
Design Solutions
As the UK's longest established Laser screed Flooring Operator, Seamless
Floors is well placed to have viewed the revolution that has occurred
during recent years in the concrete flooring industry. Flooring contractors
are now required to offer fully indemnified design and build packages
allied to an ever-expanding scope of works. Flooring solutions have to
be high quality, cost effective and exactly tailored to end user requirements.
As a result it is now essential that flooring companies become involved
at an early stage in the design process. Working closely with other teams
ensures that all design solutions are harmonised and sympathetic to other
facets of the building programme. On occasions flooring companies are
consulted too late in the design process leading to discontinuity and
a loss of dynamism. The design criterion becomes rigid and solutions are
not optimised. It is not uncommon for flooring companies to be asked to
formulate a design as the last pile is being driven at site. This could
be critical to the Contractor at tender stage and ultimately costly to
the client.
The
Design Process
Expending the time and effort to bring all parties around a table early
on in the design process proved very rewarding for Bluestone. Seamless
Floors ensured that the pile type and grid were ideally suited to the
design philosophy employed.(l) Computerised design calculations were processed
and detailed drawings and proposals were drawn up and circulated. The
elimination of the need for steel fixing allied to the integrated installation
of the gas membrane provided enormous benefits in terms of scheduling
and cost. The joint free nature of the floor design also ensures minimum
future maintenance costs for the end-user as joint degradation due to
trafficking is reduced.
The
Design
The floor was designed as a fully continuous steel fibre reinforced slab
with a pile spacing of 3.5 x 3.0m and an edge span of 2.25m. The slab
thickness was 220mm and the fibre dosage rate 40kg/m3. Unlike other Steel
Fibre Reinforced Piled Systems there is no additional requirement for
steel cages over piles and other secondary bar reinforcement. This allows
for a simple construction process and eliminates the potential for steel
fixing error at site.
There was, however, a specific factor involving a requirement for portal
ties in the building that needed a suitable design resolution. The portal
restraints were tied together within the floor depth utilising additional
loose reinforcing bars. Additional mesh reinforcement was provided at
all positions of horizontal restraint to reduce the risk of shrinkage
cracks occurring.
The design needed to accommodate a uniformly distributed loading of 32.5
KN/m2 and a portal horizontal restraint in excess of 10 tonnes.
The
Tolerance
The floor was constructed to Technical Report 34 1997 Supplement "Concrete
Industrial Ground Floors" FM2 Property 4.
The
Reinforcement
The fibres supplied by Estate Wire (a subsidiary company of TrefilArbed)
are made of a special high tensile wire. Produced primarily for piled
supported floors they are added at site directly into the concrete trucks
as they arrive using specialist machinery under the ownership and control
of Seamless Floors. This process ensures an even mix of fibres throughout
the concrete matrix ensuring specified dosage rates are achieved. The
fibres 1mm in diameter and 60mm long are undulated in shape this unique
design promotes enhanced anchoring qualities ensuring shrinkage cracks
are minimised. A joint free floor is subject to shrinkage stresses caused
by vapour loss at all ages of the concrete, shrinkage is not eliminated
but is controlled. Minute random cracking is normally expected.
Construction joints utilised were Alpha DD10 by Permaban Ltd.
The
concrete mix.
The selection of the correct concrete mix is always essential and especially
so with steel fibre reinforced technology. Aggregate grading curves are
employed to ensure successful interlock between the concrete matrix and
steel fibre reinforcement. The fines content is also controlled and graded
to aid the finishing process and enhance the finished floor product. Seamless
Floors also carried out cube testing throughout the entire construction
process to ensure concrete has met the stipulated standard.
The
Construction Process.
The laying of a gas membrane simultaneously with the concrete slab had
successfully been achieved by Seamless Floors on an earlier project in
Taunton during 2000. This experience allied to a fully trained and skilled
workforce ensured the slab was completed on schedule and within tolerance.
Work on site needed to be carefully coordinated. Concrete supply was regulated
in order to allow steel fibres to be integrated and mixed at site in a
controlled manner. This element of control was reflected throughout the
whole construction process. Concrete was directly discharged and immediately
leveled by a Somero laser machine, dry shake topping was applied by means
of an automated machine and specialist-finishing processes were employed
Power floating of the slab was subsequently carried out and a curing agent
was applied.
Health
and safety.
The importance attached to matters of health and safety on site has been
increasingly been drawn into focus in recent times, and rightly so.
All members of the Seamless Floors workforce are fully trained and aware
of potential dangers on site. Guidelines and working practices are constantly
reviewed. The company's decision to fully embrace the CSCS card scheme
a number of years ago has contributed to the skills and awareness needed
to successfully complete the project at Poole.
Conclusion,
"Value engineering" is a phrase that has been banded around
for sometime in the construction industry, but on occasions it is taken
to mean the cheapest solution to a given set of design parameters regardless
of quality considerations. During the project in Poole credit should be
given to Bluestone for achieving a high quality end product at a cost-effective
price. Paul Gale of Bluestone states " experience has told our company
that it is essential to communicate well at an early stage with all parties,
as this leads to major benefits down the line."
(1).
TAB - S. (TrefilARBED Bissen, Structural Design Procedure).
|